1.23.25 - Crewmen continue to form up the pad for the foundation pour,
1.05.25 - We're excited to be breaking ground on our next building in Binford Rd Business Park for Clover Tool Company. Dirt crews broke ground last week and are currently building the pad. The foundation should be poured this month,
10.25.24 - Construction is scheduled to begin in January.
These beautiful Industrial Suites are available for Lease or Sale! Available size ranges from 3,249 to 13,020 SF. Each space can accommodate a 2nd story office, if desired. For more information call 877-955-5755.
7.17.23 - The stucco and stone work are complete. Crewmen are installing glass.
4.14.23 - Masons started their work on the stucco. These condos will be ready by mid-May,
3.01.22 - Erectors continue to hang steel. The framing crew began framing the front facades. The paving crew will start pouring the paving soon,
12.02.22 - Erectors continue to hang rafters and began sheeting one of the buildings,
11.17.22 - Erectors are hanging the steel,
11.03.22 - Crews have formed the pads and are pouring the first of these two new facilities,
1.23.24 - This project is complete,
12.14.23 - Crewmen continue to sheet the building,
11.29.23 - Crewmen are expanding SiteOne Landscape Supply's Friendswood location by 12,000 SF. The paving was recently poured and erectors are hanging steel,
12.09.19 - This project was completed in November and SiteOne is moving in,
10.14.19 - Interior painting is underway and landscaping installation will soon follow,
9.27.19 - Painters are wrapping up. Site crew is cleaning up the site. The building should have power next week,
9.09.19 - Crews are tying steel in preparation for Wednesday's paving pour,
8.19.19 - The building is fully sheeted and trimmed. Downspouts are installed and the side canopy. Interior framing is underway,
8.09.19 - M&M Erectors continue to sheet the roof. Site crewmen are grading for paving,
7.23.19 - Crewmen are erecting the building,
7.10.19 - Crews are tying steel for tomorrow morning's pour,
6.28.19 - Sitework continues,
6.26.19 - Crews broke ground on this project last week. It will be a new 7,000 SF retail center and showroom for a wholesale landscape and irrigation supplier SiteOne. Trevor Robinson is the PM.
1.23.24 - Building is clean and landscaping is installed,
12.14.23 - Parking area striping is complete,
11.29.23 - Glass installation is complete and the ceilings are installed. Power should be turned on next with an expected completion set for next month,
10.25.23 - Interior crews are hanging sheetrock. Concrete crewmen are getting ready to pour the equipment pad,
7.25.23 - Crewmen poured the pad this morning,
7.20.23 - Crewmen are preparing for next week's pour,
5.5.23 - Crews are breaking ground on Big City Manufacturing's new facility in Industry Park. This Design/Build project includes a fully air conditioned shop and 3,000 SF of finished office space,
12.15.23 - These condos are complete and are available for Lease or Sale. Spaces range fom 2,088 SF to 12,529 SF.
10.04.23 - The buildings will have power this week and landscape installation is also on schedule for this week. These spaces are available for lease or sale,
4.20.23 - Crewmen poured the last of the paving last night. Erectors continue to sheet the condos,
3.22.23 - Erectors are hanging the steel. Half of the paving was poured this morning,
10.13.22 - Site crewmen broke ground this week on the Katy industrial condos. Crewmen have scraped the site and are starting their work on the pads,
9.22.22 - Our crews are breaking ground this week on a new Industrial Condominium project in Katy, TX. Two 11,830 SF units are under construction in the Katy-Hockley Business Park Development (4107 and 4109 Katy Hockley Rd). The condominiums will total 23,660 SF and will be ready Q2 2023.
7.06.22 - This project is complete,
6.02.22 - Masonry work is underway and electrical work continues,
3.02.22 - Erectors continue to hang steel. The pre-assembles are complete and crews are filling in the intermediate bays,
2.15.22 - Erectors are hanging sections of roof,
1.19.22 - Crews are pouring the second half of the foundation,
11.11.21 - Site work is underway for Elite RV's new 70,000 SF conceirege service storage center for motorcoaches,
6.02.22 - Crews are addressing a few punch out items and then this project will be complete,
3.02.22 - Crews have made great progress this month. The paving is complete and masonry has begun. Interior crews continue to hang sheetrock,
2.15.22 - Interior crews are hanging drywall and the concrete crewmen are forming the paving. The excavation of the business park's eastern retention pond is almost complete,
1.19.22 - Erectors are sheeting the roof. Framers are framing the walls.
1.04.22 - Erectors are hanging steel for this new facility,
12.16.21 - Crews are preparing for the foundation pour,
11.11.21 - Site work is underway for a new 20,000 SF trade school, located at 20213 Binford Rd,
6.02.22 - Power was turned on today. The ceiling tile installation and remaining flooring will continue,
7/01/21 - This new 8,600 SF office and warehouse is in permitting. Construction updates will be available on this page, so check back for this location's progress and availablility.
6.02.22 - Power was turned on today. Flooring and ceiling work will continue,
7/01/21 - This new 8,600 SF office and warehouse is in permitting. Construction updates will be available on this page, so check back for this location's progress and availablility.
4.20.21 - The rock and concrete work are completed. Fence installation and clean up remain.
4.05.21 - Crewmen continue cutting grade,
3.26.21 - Site crew began scraping for a new rock yard at 4121 Katy Hockley Rd. This is part of the new tenant’s improvemnets,
2.06.20 - This project is complete,
12.15.19 - The building is fully trimmed. Flooring began in the entry,
12.03.19 - Painting is complete and flooring will soon follow,
10.05.19 - Sheeting is underway,
9.27.19 - Parking lot is poured. Erectors are hanging steel,
9.24.19 - Crews are erecting the building. More paving has been poured,
9.12.19 - The building pad was poured and crews are forming for additional paving,
7.16.19 - Crews are pouring the main drive,
7.11.19 - Crewmen began building the pad and laying out the private road for the business park,
6.28.19 - Sitework is underway for this new 9,300 SF office/warehouse, located off Katy Hockley Road and Clay Road. This new facility is available for Sale or Lease,
8.14.20 - This project is complete,
8.06.20 - Final clean is scheduled for next week,
7.07.20 - Waiting on power,
6.12.20 - Irrigation installation is underway. The crane installation is complete. Once this project has final power, crews will complete the AC, flooring, MEP trim out, and interior office painting,
5.29.20 - The entrance canopy is installed,
5.28.20 - Stone is complete and the interior walls are two sided, taped, and floated. AC grills will be completed today,
4.21.20 - Walls and roof are sheeted. The overhead doors are being installed, and the office framing, AC work, and plumbing rough in has begun,
4.13.20 - The building is 60% complete. Crewmen started to frame the office. Paving and curbs are completed,
3.30.20 - Erectors continue to hang steel as additional crews prepare for next weeks pour,
3.25.20 - Erectors are unloading steel,
3.18.20 - The foundation was poured today,
3.13.20 - Plumbing and electrical groundout are waiting on inspections. Crews are digging grade beams and seting steel, preparing to pour next Wednesday,
3.11.20 - Crews are setting p the slab for next week's pour. Crews are also plumbing ground out for the fire line,
3.02.20 - Finishing up subgrade for paving. Steel has been delivered,
2.20.20 - Crews finished installing the storm and will continue to form the pad,
12.27.19 - Crews have begun sitework for Grizzly's new facility. Dennis Montesinos is the PM and Kenneth Whitmill is the Superintendent,
Completed project photos,
6.08.20 - Painting is near completion. This project will be completed next week, following landscaping,
5.07.20 - Masonry contractors completed the stucco. The wall tile in the restrooms is being installed. M&M Erectors are trimming the building and installing the entry canopy,
4.30.20 - Painters completed their work painting the walls and ceilings. Door frames are being installed. The masonry contractor began the stucco facade,
4.23.20 - The entry canopy is complete. Painters are spraying the exposured structure. Electricians are building the service panels,
4.14.20 - AVAdek is installing the entry pergola. HVAC ductwork is being installed. Electricians are roughing in the plugs and switches,
4.02.20 - Interior buildout continues, window and door installation are also underway,
3.10.20 - Roof sheeting and siding are underway,
3.02.20 - Crewmen have finished sheeting the east wall,
2.27.20 - Erectors continue to hang steel, and began sheeting the east wall,
2.20.20 - The building is delivered and the erectors are shaking out and assembling the steel,
2.15.20 - Crews are pouring the foundation,
2.11.20 - Crews are prepping for the foundation pour,
12.14.19 - Crewmen plan to pour paving on Monday,
12.12.19 - Site work continues,
Crewmen will soon begin constructing a new 8,000 SF office building for E Squared Marine,
12.15.19 - This property Available for Sale or Lease. Call for more information, 713-671-5300.
12.03.19 - Below are photos of the final interior,
10.05.19 - Landscaping is complete and flooring is near completion,
9.27.19 - Power has been set on the building. Landscaping is being installed. Next week the ceiling tiles and flooring will be installed,
9.13.19 - Flooring and landscape installation are underway,
8.09.19 - Electricians continue to run lights in the warehouse, while plumbers work on the waterline. Painting is underway. M&M Erectors finished trimming out the building,
7.11.19 - Masons are laying the stone. Interior crews are framing the walls. Septic tanks are being installed,
6.28.19 - This office/warehouse is now fully sheeted. Interior framing is underway, as additional crewmen frame for the next paving pours, and the erectors trim the facility,
6.06.19 - Erectors have progressed to installing the wall and skylight sheeting,
3.25.19 - Crews poured the front paving last week,
3.20.19 - Driveway is poured and the pad is complete. Concrete crews will be pouring the front half of the paving tomorrow,
This facility was purchased by Stillo Construction.
11.01.18 - The building is complete. Parking lot cleaning and striping to follow,
9.12.18 - Masons are installing the cast stone. Grid for the acoustical ceiling is being installed,
8.30.18 - Masonry work is underway as crewmen address HVAC and interior framing,
7.20.18 - Crewmen are installing exterior sheathing and are framing interior walls,
7.16.18 - Crewmen have progressed to roof sheeting,
7.06.18 - Crewmen continue to sheet the walls,
7.03.18 - All steel is hung and crewmen have progressed to sheeting the building,
6.25.18 - Crewmen began hanging steel,
5.01.18 - Paving is poured and sawcut. Crewmen begin seeding the detention pond,
4.26.18 - Crewmen poured the paving this morning,
4.12.18 - Crewmen are setting the storm for Spec Bldg 1. Electricians are trimming out electrical service panel for pond lift station and water well,
3.28.18 - Crewmen poured the foundation this morning,
3.23.18 - Excavation of the detention pond is complete. Slab is made up and ready to pour,
3.13.18 - Progress on the water tank and the detention pond,
1.09.18 - The pad is built for this new facility and crewmen are grading the detention pond. This new office/warehouse is Available for Sale or Lease, off Clay Rd in Katy,